• BRIDGEWATER POINT •

• LATEST UPDATE •

AUGUST 2018.


Block A

Reception area complete , reception counter installed , minor decoration works to be completed

•Level 1 to 4 – complete with minor final snagging and cleaning being carried out

•Level 5 – Units are 95% compete with all kitchens and sanitaryware installed, M&E second fix completed, as well as 2nd fix joinery. Finishes trades closing out the final decorations and floor finishes, followed by final sparkle clean

Corridors ceilings are all installed with decoration well progressed the floor coverings have begun to be installed through communal areas.

Block B

Due for completion – Completions to begin Start of August.

•Floors 1-2 are 95% complete with floor coverings complete and programmed works for electrical testing to commence along with water tests.

•Floors 3-4 are 90% complete with floor coverings progressing and final stages of joinery works.

•Floors 5-6 are 85% M&E second fix works being carried out along with 2nd fix joinery. Decoration continuing throughout.

•Floors 7-8 are 75% complete with final kitchens been installed and remaining plots to be mist coated.

Final Completion for Block B estimated – Mid September.  


The external podium works has steelwork, metal deck and concrete poured,  Final brickwork to façade completing, waterproofing to deck progressing well with external blockwork to follow.

The podium/carpark is due for completion beginning of september, which will also allow the release of the town houses at GF.

• COMPLETION DUE Q4 2018 •

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 1 •

• LATEST UPDATE •

AUGUST 2018


Block A  

Due for completion – Late September

  • Lower Ground – Rooms 70% completed, final plumbing works underway.
  • Ground Floor – Rooms 95% completed, currently de-snagging
  • Levels 3 to 5 – Rooms 95% completed, currently de-snagging
  • Level 6 - Rooms 80% completed, snagging underway
  • Level 7 - Rooms 80% completed, snagging underway
  • Level 8 – Rooms 70% completed, final plumbing works underway
  • Level 9 – Rooms 70% completed, final plumbing works underway


Block B 

Due for completion – Late September 

Lower Ground – Rooms 70% completed, final plumbing works underway.

Ground Floor – Rooms 95% completed, currently de-snagging

Levels 3 to 5 – Rooms 95% completed, currently de-snagging

Level 6 - Rooms 80% completed, snagging underway

Level 7 - Rooms 80% completed, snagging underway

Level 8 – Rooms 70% completed, final plumbing works underway

Block C 

Due for completion – Late August 

  • Townhouses – Rooms 60% completed, final electrical works underway
  • Lower Ground – Rooms 97% completed, flooring to be laid
  • Ground Floor – Rooms 97% completed, flooring to be laid
  • Levels 3 to 4 - Rooms 97% completed, flooring to be laid
  • Level 5 – Rooms 80% completed, snagging underway
  • Level 6 – Rooms 70% completed, final plumbing works underway
  •  

Cladding to block C – 100% completed

Brickwork to block A & B 95% completed

Groundworks complete to the perimeter of block C allowing hardlanscaping to begin

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 2 •

• LATEST UPDATE •

JULY 2018.

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 3 •

• LATEST UPDATE •

JULY 2018. 

Building foundations have commenced followed by the main concrete frame for the blocks.

• DUE FOR COMPLETION 2019 •

Next panel

Next panel

Next panel

• GREEN QUARTER 7 •

• LATEST UPDATE •

JULY 2018. 

Groundworks and substructure now complete, contiguous piled wall retains Cheetham Hill Road and surrounding properties allowing for the construction and completion of 5, half basement levels. 

The structural concrete frame is progressing well and on programme. Structural frame has now been completed from level -05 to 03.

.

• DUE FOR COMPLETION 2019 •

Next panel

Next panel

Next panel

• FORTIS QUAY •

• CONSTRUCTION ONSITE HAS COMMENCED •

JULY 2018. 

Next panel

Next panel

Next panel

• SILKHOUSE COURT •

• LATEST UPDATE •

JULY 2018. 

Floors 14 down to 3 - Practical completion end of October 2018

Floors 3 down to ground - Practical completion end of December 2018


Windows have been installed to the tower of the building from floors 15 down to 3.


Units on levels 14- 10 are 95% complete with testing to be completed

Units on levels 9 – 5 are 80% complete with flooring progressing

Units on levels 4 - 3 are 75% complete with mist coating underway.

Units on levels 2 – 1 and Ground are 30% complete, second side boarding underway


The cladding is 40% done with rails and pull tests been installed

• UNDER CONSTRUCTION •

Next panel

Next panel

Next panel

• HALE ADDRESS •

• email •

• ALTRINCHAM ADDRESS •




BANK HOUSE

OLD MARKET PLACE

ALTRINCHAM

WA14 4PA


INFO@FORTISDEVELOPMENTS.COM

FORTIS GROUP

SUITE 4

RICHMOND HOUSE

HEATH ROAD

HALE

WA14 2XP

+44(0)161 974 5860